To install the 7371-K500 Input Shelf (Full Depth) kit on the 7371 Full Function Hybrid Self-Checkout unit, follow these steps:

Note

The Input Shelf can be installed on either a Left-hand (LH) unit or a Right-hand (RH) unit. This procedure shows how to install the shelf on a Left-hand (LH) unit only as an example.

  1. Secure each Attachment Bar to the Input Shelf Plastic Top using two (2) M6 nuts, as shown in the image below.

  2. Based on the preferred Input Shelf height level, slide the mounting hooks of the Cross Bar into the third and forth slotted holes on the side of the Core Cabinet, as shown in the image below.

    Note

    Refer to the images below for the two (2) possible installation positions of the shelf.

  3. Secure the Cross Bar to the Core Cabinet using two (2) M3 screws.

  4. Attach the Input Shelf Top assembly to the Cross Bar using four (4) M6 screws, as shown in the image below.