Installing the Tri–Light/Lane Light Pole

To install the Tri-Light/Lane Light pole, follow these steps:

  1. Remove the existing Tri-Light/Lane Light Pole, if necessary. For more information, refer to Removing the Tri-Light/Lane Light Pole.
  2. Loosen the star–shaped washer around the keylock assembly.

  3. Remove the two (2) back panels from the tower assembly.
  4. Insert the Tri-Light/Lane Light cable through the opening in the side of Tri-Light/Lane Light pole and route it out the top of the pole.
    Note

    For the Tri-Light/Lane Light assembly without a camera, only the Tri-Light/Lane Light cable extender exist in the assembly.

    Tri–LightDestination Connection (Location)
    Cable ExtenderI/O Box (Tri–Light/Lane Light port)
    Ethernet (LAN) cable extenderEthernet (LAN)
    I/O Box (Power) cable extenderI/O Box (Input Belt)
    Tip

    To make routing the cable extender through the pole easier, first attach a weight (for example, a large bolt) to a long piece of string and drop the weighted end of the string through the Tri–Light/Lane Light pole. Once the string is threaded through the pole, tie the non-weighted end of the string around the cable connector and then pull the cable extender through the pole.

    Note

    If installing a secondary display, route the display cables out of the smaller hole on the back of the pole.

  5. Route the cables coming out of the unit so they align with the grooves and carefully insert the pole into the tower.

  6. Secure the pole to the tower with two (2) screws.

  7. Insert the excess cables into the opening on the Tri-Light/Lane Light pole so that the cables will not interfere with any outer items.