Routing I/O Box Cables

To route the I/O Box cables in the NCR SelfServ Checkout unit, follow these steps:

1.Install the I/O Box. For more information, refer to Installing the 7360 I/O Box.

2.Open the Upper Cabinet Door.

3.Using cable ties, wrap the cables and then tie them on corresponding lance bridges to fix the cables on the Upper Cabinet frame as shown in the image below.

4.Using cable ties, group the cables exiting to the back of the unit and then tie them on the I/O Box mounting plate as shown in the image above.

5.Route and sort cables. For more information, refer to Routing and Sorting Cables.

Note:  For more information about routing cables, refer to the SCO Release 6 Lite Cable Routing Instructions (497-0519586).

6.Close the Upper Cabinet Door.